Commercial Single Phase Service

Download the Single Phase Commercial Service (PDF)

Effective December 25, 2022

Applicability

This schedule is applicable to services that are single phase, standard voltage, and supplied through one point of delivery for general commercial use.

Availability

Service under this schedule is available at points on the Cooperative’s interconnected system where existing facilities of adequate capacity and desired phase and voltage are available, and additional investment by the Cooperative for new transmission, substation, or terminal facilities is not necessary to supply the desired service.

Meter Read

Meters will be read by the Cooperative beginning on the 24th of each month at midnight.

Monthly Charge

The Monthly Charge is the sum of the Access Charge and kWh charge at the following rates:

*Customer Class Access Charge Kilowatt-hour (kWh) Charge SREC Rate Designation, Outside Challis City Limits SREC Rate Designation, Within Challis City Limits
0 to 200 $54 $0.053 310 410
201 to 400 $79 $0.053 312 412
401 to 600 $104 $0.053 314 414
601 to 800 $129 $0.053 316 416
801 to 1000 $154 $0.053 318 418
1001 to 1200 $179 $0.053 321 421
1201 to 1400 $204 $0.053 323 423
1401 to 1600 $229 $0.053 325 425

Note: *Customer Class is determined by the amperage rating of the customer's service entrance equipment. Amperages in excess of these amounts will be extrapolated.

Minimum Charge

The monthly minimum charge shall be the Access Charge collected over 12 months.

Abandoned Service

Should a member’s service be physically disconnected for a continuous 12-month period, the Cooperative reserves the right to physically retire the service anytime thereafter.

Fees

  • Membership – $10
  • Disconnect Notice – $25
  • Returned Check – $20
  • Account Research/Special Handling – $30 per hour ($10 minimum)
  • Outages - Customer Equipment  – Actual Cost
  • Account Activation – $15
  • Connect charge - Office hours – $25
  • Connect charge - Overtime hours – Actual Cost
  • Disconnect charge:
    • At member’s request – Office hours – $0
    • At member’s request – Overtime hours – Actual Cost
  • Idle Service Fee – Access Charge Billed Monthly

Other fees may apply under special circumstances.

A 1% franchise fee has been imposed by the City of Challis on all Cooperative members whose point of electric delivery is within the corporate boundaries of the City of Challis, Idaho. This fee will be collected by the Cooperative for the benefit of the City of Challis as specified by City of Challis ordinance.

Authorization Date: September 22, 2022
Issued By: Salmon River Electric Cooperative, Inc. Board of Directors